I Think I did

(1/6) > >>

Contro:
 :-[
I Thought this was done, but don't.

Hierarchy tasks .

Before I can afford some tasks I need some previous steps necessarily done.
I work alone usually.
So a Microsoft Project or even the project manager I have with Goldmine is too heavy for me.

I would like to find a hierarchy task solver to monitor me in some tasks.

By example : I thought the project was created but even the photos and documents of that project are not moved or reference in its folder.
I thought I had introduced the codes in the step 200, but didn't.
I thought I sent the information but didn't . It's pending too.

Working alone is more confortable in the sense you can do partial task until complete. But some tasks precise interaction or a prior step finished.

So i must control some hierarchical tasks. How can I control this easily ?

Best Regards

Note : only offline. Desktop software only.

tomos:
So,
you're looking for a ToDo list type programme?
http://abstractspoon.weebly.com/

dr_andus:
Natara Bonsai (desktop version), if you can convince the owner to sell you a license.

Contro:
So,
you're looking for a ToDo list type programme?
http://abstractspoon.weebly.com/
-tomos (March 17, 2017, 05:15 PM)
--- End quote ---
May be. But simpler because I need only the critical points to remind.
I only need to remind the fundamental step.
I will try and comment.

Best Regards

Contro:
So,
you're looking for a ToDo list type programme?
http://abstractspoon.weebly.com/
-tomos (March 17, 2017, 05:15 PM)
--- End quote ---
Nice software indeed with a lot of options.
The option : New dependent Task Below Selected Task seems one of the possible hierarchies.
Or the subtasks that possibility that a task is not complete while the remain any subtask without completion.

But I think don't exist the option : New dependent Task below a group of selected tasks, not only the above one.

I would like the software as a trip of opportunities. I don't want to see an option if the conditions are not given or is a task depending of one or several above.

When an independent task is solved I would like to see the factible ones....

When I open a task list I would like to see only the independent tasks possible...

Sorry If I can't express better.

 :-[